How To Move An Office
Without Closing
The Basics
Phasing,
Explained
Most businesses cannot close for a week, and they do not have to. A phased move relocates departments in an order that keeps the company functioning, usually across consecutive weekends, with the teams who can work remotely moving first and the teams who cannot moving last. The trade off is honest and worth stating. Phasing costs more in total crew hours than one big move, because setup and travel repeat. What it buys is trading days, and for most businesses that maths is not close.
Move the flexible teams first
Anyone who can work from home for two days goes early. Anyone tied to a physical function, a lab bench, a workshop, a reception desk, goes last.
Split weeks need a working plan for both sites
During a phase you are operating in two places. Decide in advance where post goes, where meetings happen and how calls route, or those questions arrive as emergencies.
IT spans the phases and needs its own plan
You cannot phase a network the way you phase furniture. Usually the core moves in one weekend and the rest is built around that.
Phasing costs more crew hours and saves more revenue
Be clear eyed about it. Multiple setups and multiple travel legs cost real money. Trading days usually cost more.
One point of contact across every phase
The whole benefit of phasing is that each weekend should be better than the last. That only happens if the same person holds the plan throughout.
How To Phase
A Workable
Order
Phase one, storage and archive
Anything nobody touches weekly. It clears space, reduces the later phases and carries no operational risk at all.
Phase two, remote capable teams
Departments that can work from home for a day or two. They move, settle and are productive at the new site before anyone critical follows.
Phase three, the core network
Servers, network and comms, in a single planned window, timed so the remaining teams have connectivity at whichever site they are working from.
Phase four, physically tied functions
Labs, workshops, dispatch, anything that cannot operate remotely. These move over a full weekend with the largest crew.
Phase five, front of house
Reception, meeting rooms and client facing space, set last so the first visitor to the new office sees a finished space.
Decommissioning
Old space cleared to lease condition once the last phase has gone.
What Goes Wrong
The Predictable
Failures
Nobody decided where post goes
Trivial until it is not. Mail, deliveries and couriers need a single answer for the whole transition, decided at the start.
Two sites, one phone system
Calls routing to an empty office is the most visible failure a client sees. Sort this with your provider before phase one, not during.
The plan lives in one person’s head
Write it down and share it. If the person holding the plan is unavailable on the second weekend, the second weekend goes badly.
Underestimating the last phase
The teams that move last are usually the ones with the most physical equipment, and they get the least planning attention because everyone is tired by then.
Leaving decommissioning until the end
Start the exit condition conversation with your old landlord at the beginning. Discovering a restoration obligation after the last phase is expensive.
San Diego Specifics
Local Constraints
On Phasing
Phasing in San Diego runs into a few local realities. Downtown towers restrict moves to outside business hours, so each phase is a weekend and the good weekends book out early, which caps how many phases you can realistically run in a quarter. Sorrento Valley tenancies with lab space usually cannot phase the lab at all, so the lab moves in one operation and the office phases around it. Mission Valley buildings with parking structure clearance limits are slower per phase, which changes the maths on how many phases are worth running. Carlsbad campuses with grade level access phase cheaply, because setup and access cost so little each time. Our corporate relocation page covers multi site and phased moves in more detail.
FAQ
How to Move an Office Without Closing
Questions
Related
Need To Move Without Closing?
Free surveys at both sites, a written phase plan, and one point of contact across every weekend.